Projects Under Construction


C1. University Parkway Water System – Phase 2 (MA #H1-12022-DA3)

Funded By:  CDBG-DRU
A. Scope of Work:
Project consists of the installation of a 12” water main along University Parkway and 1st St. from Red Town Rd. to North St. 
B. Estimated Cost:
Construction Cost
Original Contract Amount - $694,794.00
Current Contract Amount - $713,284.00
Construction Cost To-Date - $592,405.87
Funding
CDBG-DRU Funding - $694,794.00
C. Current Status/Comments:
Contract acceptance as Substantially Complete to Police Jury. Punch List is attached. 45 day lien period ends November 13, 2016


C2. Street Rehabilitation - Phase 1 - Cold Plane, Patch, & Overlay

Funded By:  City Bond Issue
A. Scope of Work:
Anderson St.- Intersection with Westwood Dr.
Kings Rd. - Jean St. to Abe Allen Memorial Dr.
Marvin Ave. - Douglas St. to Edwards St.
E. Union St. - 6th St. to 5th St. 
B. Estimated Cost:
Construction Cost
Original Contract Amount - $158,770.00
Current Contract Amount - $158,770.00
Construction Cost To-Date -  $0.00
Funding
City Bond Issue -                $ 158,770.00
C. Current Status/Comments:
Contract has been accepted as Substantially Complete. 45 day lien period ends on April 13, 2017. 


C3. Street Rehabilitation - Phase 2 


Funded by: State Capital Outlay/ City Bond Issue

A. Scope of Work:
W. Arkansas St. - 7th St to 6th St - Reconstruction
E. Fertitta Blvd- 6th St to 5th St. - Reconstruction
Fertitta Blvd - 10th St. to 6th St. - Patch, cold plane and overlay

B. Estimated Cost:
Construction Cost:

Original Contract Amount -        $297,248.04
Current Contract Amount-         $297,248.04
Construction Cost To Date-                   $0.00

Funding:
City Bond Issue -                      $297,248.07

C. Current Status:
Contractor is scheduled to begin cutting line on Fertitta on Wednesday. Deadline for Substantial Completion is May 21, 2017

C4. Potable Water System Contract I- Hwy 28 Water Line Replacement at Ellis St.

Funded by: Drinking Water Revolving Loan Fund

A. Scope of Work:
Replace the 2" water line on the south side of LA 28 with an 8" line between LA 1213 and Elllis St.

B. Estimated Cost:

Construction Cost:
Bid from Apeck Construction-  $61,479.10

Funding:
DWRLF Grant $14,800.00
DWRLF Loan- $59,200.00
Total Project Cost- $74,000.00

C. Current Status:
Contractor began work last week installing the bore under LA 1213 and Lebo's.